Direct answer: for a 100-150 m² single-family house on one or two levels, plan for 300 to 600 fifty-kg bags of cement, all work packages included — foundations, walls, slab and plaster. The usual rule of thumb on Moroccan sites is 3 to 4 bags per square metre of floor area. But that figure swings by a factor of two with surface, number of storeys, soil nature and finish level: only a package-by-package count gives a defensible number.
A house is built in packages, each consuming its own concrete or mortar at its own mix ratio. Foundations and structural elements are cast at 350 kg/m³ with CPJ 45 or CPJ 55 cement, a slab on grade needs 300 kg/m³, masonry and plaster work with mortar dosed at 250-350 kg/m³. The total is built by pricing each volume — not by applying a random lump sum.
| Package | Typical volume (100 m² house) | Mix ratio | 50 kg bags |
|---|---|---|---|
| Foundations and footings | 15-25 m³ | 350 kg/m³ | 105-175 |
| Slab on grade | 10-12 m³ | 300 kg/m³ | 60-72 |
| Walls and tie beams | 8-15 m³ (concrete) | 350 kg/m³ | 56-105 |
| Masonry mortars | 6-10 m³ | 250-350 kg/m³ | 30-70 |
| Interior and exterior plaster | 400-600 m² | 250-300 kg/m³ | 100-180 |
Total: 350 to 600 bags for a complete house, more for a two-storey build — the structural share (columns, beams, upper floor) takes over from masonry. Conversely, a hollow-block build with modest plaster and a hollow-core floor stays at the bottom of the range.
The calculation is a simple chain: volume x ratio / 50. First the volume: length x width x thickness for each concrete pour, wall area x joint thickness for masonry. Then the ratio: 350 kg/m³ for reinforced concrete, 300 for slabs, 250-350 for mortars. Finally the conversion into 50 kg bags.
Concrete example for a 20 m² terrace slab, 12 cm thick: 20 x 0.12 = 2.4 m³ of concrete. At 300 kg/m³, the requirement is 2.4 x 300 = 720 kg of cement, i.e. 15 bags of 50 kg (14.4 rounded up). Add 5-10% for waste and touch-ups: order 16 bags and gain peace of mind.
Our dosage calculator turns these rules into figures for your exact volumes, package by package. And because a site never stops to wait for a truck, DAM delivers CPJ 45 and CPJ 55 cement within 24h in Dakhla — bags, big bag or bulk — at per-tonne posted prices, no quote surprises. Structural design belongs to the engineer: these orders of magnitude serve the budget, never the design calculations.
Foundations, walls, slab, plaster, columns: each package consumes its own concrete or mortar at its own mix ratio.
Length x width x thickness for each concrete pour; wall area x joint thickness for masonry.
Reinforced concrete 350 kg/m3, slab on grade 300, mortar 250-350: volume x ratio = kilograms of cement.
One cubic metre of concrete at 350 kg/m3 takes 7 bags; at 300 kg/m3, 6 bags. Always divide by 50.
+5-10 % for waste and touch-ups: running short mid-pour costs more than the margin.

3,500 to 6,000 MAD/m² excluding land, sector orders of magnitude: the three tiers of the budget, Dakhla specifics and the cement line — the only one you can lock at a firm price.
Read article
40-80 MAD/T for sand, 60-120 MAD/T for gravel ex-quarry: aggregate classes, price factors and the real cost of cheap aggregate. DAM sells cement, not aggregates.
Read article
Corrosive chlorides for one, excessive fineness for the other: why quarry aggregate remains the rule in coastal zones, and how to secure local sands.
Read articleOur team responds within 24h. CPJ 45 on request, CPJ 55 on request. Delivery within Dakhla included.