Why Choose Bulk Packaging?

by Dakhla Aménagement Team

Why Choose Bulk Packaging?

Bulk packaging represents the most economical and ecological solution for large-scale construction sites. The cement is delivered by tanker truck and pumped directly into storage silos on site, eliminating the costs and waste associated with packaging. This method represents a significant saving on the unit cost of cement.

In terms of logistics, bulk offers considerable advantages. A tanker truck can transport up to 30 tonnes of cement, compared to 26 tonnes in bags. Unloading time is halved: 30 minutes for a bulk truck compared to over an hour for manual unloading of bags. This efficiency translates into smoother construction sites and less labor devoted to handling.

In terms of quality, bulk better preserves the properties of the cement. Unlike bags that are exposed to moisture and repeated handling, cement in silos remains protected from humidity and contamination. The loss of strength due to aging is also reduced, as cement in silos is generally consumed more quickly than a stock of bags.

Dakhla Aménagement has a fleet of modern tanker trucks equipped with high-pressure pumping systems, capable of supplying silos located several tens of meters in height. Our logistics service ensures bulk delivery throughout Southern Morocco and in Mauritania, with deadlines of 24 to 72 hours depending on the zone.

Need cement for your project?

Key steps

  1. 1

    Évaluer le volume nécessaire

    Le vrac nécessite un minimum de 30 tonnes. Calculez votre besoin total pour optimiser le coût.

  2. 2

    Vérifier la présence d'un silo

    Le vrac nécessite un silo de stockage sur chantier. Vérifiez sa capacité et son accessibilité.

  3. 3

    Préparer l'accès camion

    Assurez que le camion-citerne (30T) puisse accéder au silo : aire de manœuvre, solidité du sol.

  4. 4

    Planifier la livraison

    Contactez DAM au +212 658-265685 pour planifier. Délai 24h à Dakhla, 72h dans le Sud marocain.

  5. 5

    Pomper le ciment

    Le chauffeur connecte le tuyau de pompage au silo. Le ciment est transféré automatiquement en 20-30 min.